Week ten is in the books. Week eleven should be interesting!

So a lot more interior stuff done last week... first coat of paint finished and the cement put down for the bathrooms for the tiles.
2011 Appleton Way Week Ten Complete

Saturday, October 1, 2011

Week nine is done, heck week ten is also almost done.

OK. So I've finally updated week nine pictures.... since this is so late in the week, I was tempted to just wrap up these images with the week ten ones which should be coming on Tuesday. I'll get back on track next week! -enjoy.
2011 Appleton Way Week Nine

Thursday, September 22, 2011

Week Eight in the books!

Apologies for not updating this sooner. We went on vacation and things have been pretty busy.
Week Eight Complete

Tuesday, September 13, 2011

Week Seven Complete!

So we are almost two months in and things are (so far) looking very positive. Mike, our main contractor is taking a ten day vacation so hopefully everything goes smoothly while he's away. We mostly have interior stuff for this last week and I suspect this week will be more interior.

Week Seven Complete

Sunday, September 4, 2011

Week Six Complete

OK, so the workers were busy trying to get the house ready for a big inspection. This inspection covered foundation, rough electric and rough plumbing (everything passed).

Also, they wrapped the outside of the house to prepare for putting insulation in and (hopefully drywall) for week seven. Had to reinforce the old 'outside' wall too.

So, hopefully all will go well in week seven and that update will be worthwhile.

Appleton Way Week Six Complete

Tuesday, August 23, 2011

Tuesday, August 16, 2011

Monday, August 1, 2011

Remodel Week One.

Pictures of week one work!


Click here for the whole album.

Remodel 'before' pictures.

So we are planning on converting our master suite into 2+1 and then add a new suite on top. Here are some pictures of what our house looked like before the work started.



Click Here for the 'Before' Pictures.